City Manager Reports to Council
On August Activity

 

From City of Sulphur Springs

 

THE SQUARE – The Oak Street reconstruction project began today. It will include Oak/College intersection and the segment adjacent to the courthouse, but not the intersection with Jefferson.  After this project is complete we will reconstruct the Oak/Jefferson intersection and the segment of Jefferson from Oak to Church.  Then we will reconstruct the Church/Jefferson intersection.

 

EAST SHANNON WATERLINE PROJECT – This project is progressing slowly.  The contractor had difficulties, but it should be completed soon.

 

SUMMER PAVING PROGRAM – The summer paving program is progressing well.  So far the following streets have been finished:  Thomas, Majors, Vicki, Betty, Buford, Connally, Georgia, Lakeview, Holiday, Bell, Hines, Century Lake, and Irwin.  This leaves Highland, S. Davis, Lee and League.

 

NEW CITY HALL – The newly erected scaffolding is a sign that the lead-based paint abatement contractor is preparing to begin his work.  The project is beginning in earnest.

 

CLAIMS - We had one minor workers’ compensation claim in August for a laceration.

 

We had two liability claims in July.  One was for a minor collision between a patrol car and a Hopkins County Sherriff patrol truck.  The other was for damage to a car, apparently caused by a city mowing crew.

 

REVENUES AND EXPENDITURES – Finance Director, Peter Karstens will present a year-to-date review of revenues and expenditures.

 

 

                                                                                                      

 

 

MISCELLANEOUS –   Elsewhere around the City, employees:

 

_____