City Manager Reports to Council
On August Activity
From City of Sulphur Springs
THE SQUARE – The Oak Street reconstruction project began today. It will include Oak/College intersection and the segment adjacent to the courthouse, but not the intersection with Jefferson. After this project is complete we will reconstruct the Oak/Jefferson intersection and the segment of Jefferson from Oak to Church. Then we will reconstruct the Church/Jefferson intersection.
EAST SHANNON WATERLINE PROJECT – This project is progressing slowly. The contractor had difficulties, but it should be completed soon.
SUMMER PAVING PROGRAM – The summer paving program is progressing well. So far the following streets have been finished: Thomas, Majors, Vicki, Betty, Buford, Connally, Georgia, Lakeview, Holiday, Bell, Hines, Century Lake, and Irwin. This leaves Highland, S. Davis, Lee and League.
NEW CITY HALL – The newly erected scaffolding is a sign that the lead-based paint abatement contractor is preparing to begin his work. The project is beginning in earnest.
CLAIMS - We had one minor workers’ compensation claim in August for a laceration.
We had two liability claims in July. One was for a minor collision between a patrol car and a Hopkins County Sherriff patrol truck. The other was for damage to a car, apparently caused by a city mowing crew.
REVENUES AND EXPENDITURES – Finance Director, Peter Karstens will present a year-to-date review of revenues and expenditures.

MISCELLANEOUS – Elsewhere around the City, employees: